Inspection Instructions
- All inspections
require 24-hour advance scheduling. All inspections scheduling
must be made through
our computerized inspection phone line: 372-7370.
Inspections may be phoned in until midnight the day before the
inspection is needed. Please call 379-1535 with any problems or
questions.
- Authorization
Number: The computerized inspection system will generate an authorization
number during your scheduling. Keep this number.
- Footing Inspections
are required before concrete is poured. Footing Inspections must
be scheduled through the computerized inspection line the day
before. At that time you will be given an authorization number.
Then on the morning of the inspection, phone the inspectors 379-1535
between 8:00 AM and 9:00 AM to schedule a time for the inspector
to inspect the footing that day (between 9:00 AM and 4:00 PM).
You will need to provide the permit number, location, authorization
number and time you wish the inspection.
- Under-slab
Inspections are required before placing fill. All mechanicals
must be exposed.
- Basement
Foundation Inspection is required before backfill. The drainage
tile, gravel, insulation and damp-proofing must be in place.
- Crawl-Space
Foundation Inspection is required before backfill. The drainage
tile, gravel, insulation, anchor bolts, grading and sump pit must
be in place.
- Rough-In
Inspection includes frames, firestop, electrical, plumbing, HVAC,
completed roof, and manufactured fireplaces. Electrical service
should be ready for meter installation.
- Final Inspections:
All fees
and fines must be paid before final inspection will be scheduled.
Do not occupy before this inspection!
Inspectors
have all day to make requested inspections, but will try to accommodate
specific circumstances if possible.
|